File #: 2026-1513   
Type: Airport Advisory Board Agenda Item Status: Agenda Ready
File created: 6/1/2026 In control: Airport Advisory Board
On agenda: 6/9/2026 Final action:
Title: 2026 OCF Airfield Paint Project in the amount of $74.328.62
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted By: Jenn Marvin

presenter

Presentation By: Matt Grow

end

Department: Aviation

FORMAL TITLE:

title

2026 OCF Airfield Paint Project in the amount of $74.328.62

end

OCALA’S RELEVANT STRATEGIC GOALS:

Operational Excellence, Quality of Place

PROOF OF PUBLICATION:

N/A

body

BACKGROUND:

 

The Ocala International Airport (OCF) conducts routine airfield pavement marking maintenance to ensure continued compliance with federal and state standards and to promote safe and efficient aircraft operations.

 

This project includes cleaning and restriping of runway designation numerals and centerline on Runway 8/26, cleaning and restriping of the Runway 18/36 centerline, and cleaning and restriping of various Taxiway A markings.

 

All work will be performed in accordance with applicable standards, including FAA Advisory Circular 150/5340, Standards for Airport Markings, the Innovative Pavement Research Foundation Airfield Marking Handbook (IPRF01-G-002-05-1), and Chapter 14-60 of the Florida Administrative Code.

 

The project will be completed utilizing the State of Florida bid contract with Florida Airfield Maintenance, JV, which allows for efficient procurement and competitive pricing.

 

Staff submitted a grant application to the state that was denied for their fiscal year 2026. A new request for FY 2027 will be made but worst case scenario the project will be funded 100% in house.

 

FINDINGS AND CONCLUSIONS:

 

Staff recommends approval and authorization for the appropriate City officials to execute all related documents.

 

FISCAL IMPACT:

 

Funding for this project will be provided as follows:

 

                     Local Share: $74,328.62                     

                     Total Project Cost: $74,328.62

 

No grant funding is associated with this project.

 

PROCUREMENT REVIEW:

N/A

 

LEGAL REVIEW:

N/A

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny