Skip to main content
City of Ocala Logo

  For historical data from all meetings prior to January 18, 2022, please refer to our archived meeting repository.

File #: 2026-0432   
Type: Agenda Item Status: Agenda Ready
File created: 12/9/2025 In control: City Council
On agenda: 1/20/2026 Final action:
Title: Award of the contract to replace the HVAC chiller for City Hall and Citizen Service Center to Sherman Mechanical Contractors in an amount not to exceed $363,668
Attachments: 1. FOR COUNCIL - 275-Ton Air-Cooled Chiller Replacement Agreement - Sherman Mechanical Contractors, LLC (FAC 260128), 2. BID TABULATION
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.
Submitted By: Christina Guy
presenter
Presentation By: Gary Crews
end
Department: Facilities Management

FORMAL TITLE:
title
Award of the contract to replace the HVAC chiller for City Hall and Citizen Service Center to Sherman Mechanical Contractors in an amount not to exceed $363,668
end

OCALA'S RELEVANT STRATEGIC GOALS:
Quality of Place

PROOF OF PUBLICATION:
Bid released to the public: October 30, 2025

body
BACKGROUND:
The HVAC chiller serving City Hall and the Citizen Service Center is 14 years old, has reached the end of its useful life, and is frequently experiencing mechanical issues. This has resulted in elevated maintenance costs, diminished cooling efficiency, and inconsistent temperature control throughout the buildings. Given its age and condition, further repairs are no longer economically feasible and pose a risk of total system failure, which would significantly disrupt staff operations and public services. Replacing the chiller will enhance energy efficiency, reduce long-term maintenance expenses, and ensure reliable climate control for employees and visitors.

FINDINGS AND CONCLUSIONS:
On October 30, 2025, the City issued Invitation to Bid (ITB) No.: FAC/260128 for the replacement of the 275-ton air-cooled HVAC chiller for City Hall and the Citizen Service Center. Six competitive bids were received, one of which was subsequently withdrawn. Sherman Mechanical Contractors was found to be the lowest responsive and responsible bidder as follows:

Facilities staff recommends approval of the award of Contract No. FAC/260128 to Sherman Mechanical Contractors for the replacement of the 275-ton air-cooled HVAC chiller with an estimated cost of $363,668.

FISCAL IMPACT:
Funding is allocated in account 001-012-601-512-51-46010 - CMO-Facilities CIP Maintenance.

PROCUREMENT REVIEW:
These services were procured in compliance with the City's Procurement Policy.

LEGAL REVIEW:
This Agreement will be reviewed and approved for form and lega...

Click here for full text