Submitted By: Eric Giannino
presenter
Presentation By: Sean Lanier
end
Department: Engineering
STAFF RECOMMENDATION (Motion Ready):
title
Approve agreement with Platform Group, LLC for design-build services for the Ocala Skate Park Expansion Project in the amount of $884,561, plus a 10 percent contingency amount of $88,457, for a total expenditure of $973,018
end
OCALA'S RELEVANT STRATEGIC GOALS:
Quality of Place, Operational Excellence
PROOF OF PUBLICATION:
Bid released to the public: 8/21/2024: Newspaper ad published 8/23/2024
body
BACKGROUND:
Opened in December 2018, the Ocala Skate Park is a 6.02-acre facility located at Tuscawilla Park in the heart of Ocala's developing downtown. The Skate Park is open daily from sunrise to 10:00 p.m. and, in addition to its existing 10,000-square-foot street course, offers a dedicated parking lot, public art, and picnic areas for its patrons.
FINDINGS AND CONCLUSIONS:
On August 21, 2024, the City issued Request for Proposals ("RFP") No. ENG/240466 seeking competitive proposals from qualified professional design-build teams to provide conceptual and final designs, construction documents, and construction services for the completion of the Ocala Skate Park Expansion Project (the "Project"). This Project includes the construction of four new recreational phases for the Ocala Skate Park.
On September 25, 2024, the City received one qualified and responsive proposal from Platform Group, LLC ("Platform Group"). A Selection Committee met on October 30, 2024, to evaluate the qualifications and experience of the proposer, and again on November 20, 2024, to evaluate project understanding, design and construction approach, and project cost and feasibility. After oral presentations, the Selection Committee recommended an award to Platform Group, LLC.
Ocala Skate Park Expansion Phases B, C, D, and E are projected to be completed in December 2025.
Phase B - Intermediate Bowl
Phase C - Snake Run
Phase D - Large...