Legislation Details

File #: 2027-0008   
Type: Agenda Item Status: Agenda Ready
File created: 9/17/2026 In control: City Council
On agenda: 10/20/2026 Final action:
Title: Contract with Commercial Industrial Corp. to provide all labor, materials, equipment, and services required to complete the Ocala International Airport Runway 36 Runway Safety Area Grading for a total expenditure not to exceed $379,282
Attachments: 1. FOR COUNCIL - Construction Services Agreement for Runway 36 RSA Grading - Commerical Industrial Corp (AIR 260692), 2. OCF-SOG-3-12-0055-038-2026-Grant Agreement, 3. Res 2026-50 - executed, 4. BR 2026-156 -executed, 5. BID TABULATION
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.
Submitted By: Paul Constable
presenter
Presentation By: Sean Lanier
end
Department: Engineering
/
FORMAL TITLE:
title
Contract with Commercial Industrial Corp. to provide all labor, materials, equipment, and services required to complete the Ocala International Airport Runway 36 Runway Safety Area Grading for a total expenditure not to exceed $379,282
end
/
OCALA’S RELEVANT STRATEGIC GOALS:
Operational Excellence
/
PROOF OF PUBLICATION:
Bid released to the public: 4/24/2026; Newspaper ad published: 4/24/2026
/
body
BACKGROUND:
A recent assessment determined that the approach end of Runway 36 no longer meets Federal Aviation Administration (FAA) runway safety area standards because grade variations and surface depressions exceed allowable design tolerances.

On August 18, 2026, the City adopted Budget Resolution 2026-156, authorizing the acceptance and appropriation of funds from the FAA in the amount of $406,165 and matching funds of $21,377. Subsequently, the Florida Department of Transportation (FDOT) has provided additional funds totaling $17,102, expected to be adopted on 10/20/2026, which in turn reduces the required matching funds by the same amount. The FAA and FDOT grants and match funds the construction phase of the Ocala International Airport (OCF) Runway 36 Runway Safety Area (RSA) Grading project.

FINDINGS AND CONCLUSIONS:
On April 24, 2026, the City issued its Invitation to Bid (“ITB”) No.: AIR/260692 for OCF Runway 36 RSA Grading. On May 26, 2026, three bids were received on a unit price basis as follows:

/

Commercial Industrial Corp. (CIC) was the lowest responsible bidder, with a total bid of $344,801.40.

Staff requests a 10 percent contingency in the amount of $34,480 to allow the City Engineer to issue change orders to cover unforeseen conditions and other conflicts that may arise during construction. With the contingency, the total project budget is not to exceed $379,281.40.

CIC has previously completed similar construction...