BACKGROUND:
The proposed project is a commercial subdivision comprising seven lots and two tracts totaling 35.01 acres.
The developer is TBMI II, LLC.
Kimley-Horn and Associates prepared the plan.
The property is zoned Planned Development (PD).
Key Points:
* A traffic study has been approved for this development.
* Access to the adjacent publicly maintained roadways was established under the PD plan approved for this development.
* The plan proposes a 50-foot-wide, future cross-access and utility easement, which will provide access to lots three, four, five, and six. If any of these lots are developed separately from the others, construction of the cross-access road will be required in accordance with the subdivision improvement plan.
* A 50-foot right-of-way is proposed for access to lots one and two and will be constructed with the subdivision improvements.
* The proposed road, potable water, gravity sewer, and drainage system will be privately maintained by the association established for the development.
* The lift station and force main are proposed for public maintenance.
Updated Conceptual Subdivision Plan:
* After the Planning and Zoning Commission hearing, staff worked with the applicant to include a note on the attached "Updated Sheet CS02: Conceptual Subdivision Plan." Specifically, this note provides further clarification to ensure that no internal lot access directly to adjacent publicly maintained roadways is addressed through the Developer's Agreement.
FINDINGS AND CONCLUSIONS:
* The conceptual subdivision plan is designed in accordance with the approved PD Plan and Standards Book.
* Access to the individual lots will be from the internal road system. No lot with...