File #: 2025-0754   
Type: Agenda Item Status: Passed
File created: 2/18/2025 In control: City Council
On agenda: 7/15/2025 Final action: 7/15/2025
Title: Approve additional expenditures for field service assembly and testing services for power transformers under the agreement with Virginia Transformer in the estimated amount of $98,700
Attachments: 1. FOR COUNCIL - GA605C - Change Request Form, 2. FOR COUNCIL - GA634A - Change Request Form, 3. Exhibit G - Optional Pricing Terms - ELE-24044, 4. Fully Executed - Amendment 1 - Supply, Delivery, Installation and Testing of Power Transformers (ELE 240044), 5. Fully Executed - Agreement for Supply, Delivery, Installation and Testing of Power Transformers - Virginia Transformer Corp (ELE, 6. Council Report - Purchase of Power Transformers - Virginia Transformer Corp (ELE 240044) 3-5-24

Submitted By: Robert Whitehead

presenter

Presentation By: Doug Peebles

end

Department: Electric Utility

STAFF RECOMMENDATION (Motion Ready):

title

Approve additional expenditures for field service assembly and testing services for power transformers under the agreement with Virginia Transformer in the estimated amount of $98,700

end

OCALA’S RELEVANT STRATEGIC GOALS:

Fiscally Sustainable

PROOF OF PUBLICATION:

N/A

body

BACKGROUND:

On March 5, 2024, City Council approved the purchase of three power transformers, spare parts, and service assembly from Virginia Transformer Corp. Two transformers were designated to replace aging infrastructure at the Airport Substation, while the third was for the Shaw Substation.

 

FINDINGS AND CONCLUSIONS:

Virginia Transformer Corp. issued a Change Request Form to Ocala Electric, providing notice that the original contract estimates of $39,597 per unit for optional Field Service Testing and Assembly services had increased by $47,000 to $86,597.

 

Ocala Electric is expecting delivery of two units at the Shaw and Airport Substations and requests approval for an increase in expenditure in the amount of $98,700, representing the price increase of the two transformer units and a five percent contingency. 

 

FISCAL IMPACT:

Funding for the increased expenditure is budgeted in the project accounts detailed below.

                     Airport Substation account #332-032-184-531-69-65010 = $47,000

                     Shaw Substation account #332-032-183-531-69-65010 = $47,000

                     Five percent contingencies for specialty equipment will be charged to the appropriate Substation account = $4,700

Grand Total $98,700

 

PROCUREMENT REVIEW:

These goods and services were procured in compliance with the City’s Procurement Policy. 

 

LEGAL REVIEW:

The underlying Agreement has been reviewed and approved for form and legality by City Attorney, William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny