Title: Renewal of agreement for professional electric transmission design and engineering services with GAI Consultants, Inc., in an amount not to exceed $2,500,000
Attachments: 1. FOR COUNCIL - First Amendment - Professional Electric Transmission Design - GAI Consultants, Inc (ELE 211020), 2. Agreement for Professional Electric Transmission Design and Engineering Services, 3. Council Report - 12-20-22 - Electric Transmission Design and Engineering (ELE 211020)
Related files: 2022-0847
Submitted By: Brittany Craven
presenter
Presentation By: Doug Peebles
end
Department: Electric Utility

FORMAL TITLE:
title
Renewal of agreement for professional electric transmission design and engineering services with GAI Consultants, Inc., in an amount not to exceed $2,500,000
end

OCALA'S RELEVANT STRATEGIC GOALS:
Engaged Workforce, Operational Excellence

PROOF OF PUBLICATION:
N/A

body
BACKGROUND:
Ocala Electric Utility ("OEU") currently maintains a professional engineering services agreement with GAI Consultants, Inc. ("GAI"), to provide comprehensive design and construction management services for electric substations, transmission, and distribution facilities, as well as other related engineering services. These services are essential to support ongoing and future electric system reliability and capacity projects, including substation upgrades, transmission relocations, and system modernization initiatives.

GAI provides specialized expertise in the following areas:
1. 230kV and 69kV transmission utilizing steel and concrete poles and caisson foundations.
2. 230kV, 69kV, and 12kV overhead and underground lines.
3. 230kV, 69kV, and 12kV substation design and upgrades.
4. Protective relaying schemes, foundation design, and substation ground grid evaluation.
5. Civil and geotechnical engineering, including site work, stormwater, and barrier design.

Under the current agreement, GAI has supported critical projects, including the Airport 814 Feeder Upgrade, planning for the relocation of Leo White Substation, and the addition of a fourth 12kV distribution transformer at the Shaw Substation.

FINDINGS AND CONCLUSIONS:
On December 20, 2022, City Council approved the award of Contract No.: ELE/211020 to GAI for an initial term of three years. The contract allowed for a single two-year renewal term. The services provided by GAI have been satisfactory and essential to maintaining the reliability, safety, and capacity of the City's electric infras...