Submitted By: Samuel Grant
presenter
Presentation By: Sean Lanier
end
Department: Engineering
STAFF RECOMMENDATION (Motion Ready):
title
Approve award of the contract for construction services for the annual sidewalk maintenance and repair program to Marion Rock, LLC, in an amount not to exceed $600,000
end
OCALA'S RELEVANT STRATEGIC GOALS:
Quality of Place, Operational Excellence
PROOF OF PUBLICATION:
Bid released to public: 5/15/2025; Newspaper ad posted: 5/16/2025
body
BACKGROUND:
Multiple City of Ocala (City) departments will utilize this agreement for various concrete projects on City property and along rights-of-way throughout the City. These projects will encompass a wide range of services including, but not limited to, concrete sidewalks, concrete driveways, concrete removal, curbing, curb ramps, conduit, handrails, traffic separators, concrete curb and gutter removal and replacement, mitered ends, decorative concrete, end walls, and sod.
FINDINGS AND CONCLUSIONS:
On May 15, 2025, the City of Ocala issued Invitation to Bid (ITB) No.: CIP/250657 for the provision of construction services for the annual sidewalk maintenance and repair program. On June 16, 2025, three vendors responded to the solicitation on a line-item price basis using sample projects as follows:
Marion Rock, LLC (Marion Rock) was found to be the lowest responsive and responsible bidder. This contractor has completed similar projects for the City in the last five years. Marion Rock is a local contractor and their experience is well documented.
Engineering recommends the approval of the contract for an amount not to exceed $600,000 over the initial two-year term. The contract provides the City with an option to renew for two additional one-year terms. Any price increase for contract renewals will be subject to negotiation as approved by the City of Ocala. In no case will the increase exceed 3 percent annually.
FISCAL IMPACT:
Funding for this contract for Fisca...