File #: 2024-1695   
Type: Agenda Item Status: Agenda Ready
File created: 6/13/2024 In control: City Council
On agenda: 7/2/2024 Final action:
Title: Approve contract award to Art Walker Construction, Inc. for the construction of the North Development Access Road project in the amount of $1,949,000, plus a 10 percent contingency, for a total expenditure not to exceed $2,143,900
Attachments: 1. FOR COUNCIL - Construction Services Agreement for North Side Access Road at Ocala International Airport - Art Walker Construction, Inc (AIR 240533), 2. BID TABULATION, 3. Bid Documents - Art Walker Construction, Inc., 4. Future Development North Road Phases, 5. NDAR Newspaper publications04172024, 6. Plan Set - North Development Road, 7. Fully Executed - Original PTGA for North THangar Access Road (449858-1-94-01), 8. Fully Executed - First Amendment - PTGA for North THangar Access Road - Executed (FM 449858-1-94-01)
Related files: BR-2024-150
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.
Submitted By: Paul Constable
presenter
Presentation By: Sean Lanier
end
Department: Engineering

STAFF RECOMMENDATION (Motion Ready):
title
Approve contract award to Art Walker Construction, Inc. for the construction of the North Development Access Road project in the amount of $1,949,000, plus a 10 percent contingency, for a total expenditure not to exceed $2,143,900
end

OCALA'S RELEVANT STRATEGIC GOALS:
Operational Excellence

PROOF OF PUBLICATION:
4/17/2024

body
BACKGROUND:
The Ocala International Airport's existing T-hangar campus is at capacity and currently unable to accommodate the 40+ people on its hangar wait list. A new campus is proposed north of the "crosswind" runway and south of State Road 40 (SR 40), sized to accommodate ten buildings with ten t-hangars each, framed with larger 60x60 privately owned hangars. This new development will accommodate aviation growth for decades into the future.

To access the new campus, staff proposes to extend a road from near the intersection of SW 67th Avenue and SR 40 through the northern section of the airport. Phase I of the new roadway will serve the future hangar campus and open the area for non-aviation development. Phase II will continue eastbound and ultimately tie in with SW 60th Avenue in the future.

FINDINGS AND CONCLUSIONS:
On April 17, 2024, the City issued Invitation to Bid No. AIR/240533 for construction of the North Development Access Road at Ocala International Airport. Bids were closed on May 23, 2024. Four bidders responded and Art Walker Construction, Inc. was found to be the lowest responsive and responsible bidder.
Art Walker Construction's bid price is $1,949,000.07.

The Airport Advisory Board supports this project. Staff recommends approval of the contract with Art Walker Construction, Inc. for $1,949,000 plus a 10 percent contingency ($194,900) to allow the City Engineer to approve change orders for unforeseen conditions.
Project Expense Summary:
Design: $ 354,034...