File #: 2023-0854   
Type: Agenda Item Status: Passed
File created: 3/30/2023 In control: City Council
On agenda: 4/18/2023 Final action: 4/18/2023
Title: Approve increased expenditure under the piggyback/cooperative purchasing agreement between the City of Ocala and SGS Contracting Services for emergency repairs to the Softening Basin Lime Accelerator #1 and Lime Silo, with an additional 10% contingency added to the existing contract amount for a total contract not to exceed $1,255,196
Attachments: 1. FOR COUNCIL - SGS Contracting Services, Inc. Change Order, 2. FULLY EXECUTED - Amendment 1 - Piggyback Renewal - General Contractor for General Services (WRS 211055), 3. FULLY EXECUTED - Original Piggyback - General Contractor for General Services - SGS Contracting Services - City of Gainsville (WRS-211055), 4. GRU Agreement - SGS (2019-039-L), 5. GRU Amendment 1 (Renewal) - SGS (2019-039-L)
Submitted By: Jimmy Lopez
presenter
Presentation By: Sean Lanier
end
Department: Engineering

STAFF RECOMMENDATION (Motion Ready):
title
Approve increased expenditure under the piggyback/cooperative purchasing agreement between the City of Ocala and SGS Contracting Services for emergency repairs to the Softening Basin Lime Accelerator #1 and Lime Silo, with an additional 10% contingency added to the existing contract amount for a total contract not to exceed $1,255,196
end

OCALA'S RELEVANT STRATEGIC GOALS:
Operational Excellence

PROOF OF PUBLICATION:
N/A

body
BACKGROUND:
Water Treatment Plant No. 1 (WTP #1) was built in early 1970s, and Basin #1, the oldest of the two basins, has severe structural deterioration which required emergency rehabilitation and repair. Basin #2 is approaching three years of in-service time while Basin #1 has been undergoing repair. The average in-service time for a softening basin is 12 months. With Basin #1 still out of service, there is no redundancy in the event of a problem occurring in Basin #2.

After a competitive solicitation process, Gainesville Regional Utility ("GRU") awarded GRU Contract No. 2019-039-L (the "GRU Agreement") for general contractor services to SGS Contracting Services, Inc. (SGS) on June 10, 2019, for a term commencing on execution and ending on April 30, 2022. The GRU Contract offered two optional one-year extensions upon mutual agreement of the parties.

After evaluation of GRU's general contractor solicitation and the bid offered by SGS in response, Procurement staff determined that the use of an intergovernmental cooperative purchasing method would maximize best value to the City for services related to the repair of Basin #1 at WTP #1. On January 4, 2022, Council approved a piggyback agreement with SGS (Contract No. WRS/211055) in the amount of $1,141,087 for a term ending on April 30, 2022, and adopting the two optional one-year renewal terms available under the GRU Agreement.



On M...