Skip to main content
City of Ocala Logo

  For historical data from all meetings prior to January 18, 2022, please refer to our archived meeting repository.

File #: 2026-0674   
Type: Agenda Item Status: Agenda Ready
File created: 1/28/2026 In control: City Council
On agenda: 4/7/2026 Final action:
Title: One-year renewal of the contract with Marion Rock, LLC, for the Drainage Rehabilitation Improvement Program with an aggregate expenditure not to exceed $1,250,000
Attachments: 1. FOR COUNCIL - Amendment 3 - Construction Services Agreement for Drainage Rehabilitation Improvement Program Projects (CIP 230150), 2. Vendor Pricing Increase Notice, 3. Fully Executed - Amendment 2 - Drainage Rehabilitation Improvement Program - Marion Rock, LLC (CIP 230150), 4. Council Report DRIP 4-15-25, 5. Fully Executed - First Amendment to Construction Services Agreement for Drainage Rehabilitation Improvement Program Projects (CI, 6. Fully Executed - Drainage Rehabilitation Improvement Program (CIP 230150), 7. Council Report DRIP 4-18-23
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted By: Kyle Matvejs

presenter

Presentation By: Sean Lanier

end

Department: Engineering

FORMAL TITLE:

title

One-year renewal of the contract with Marion Rock, LLC, for the Drainage Rehabilitation Improvement Program with an aggregate expenditure not to exceed $1,250,000

end

OCALA’S RELEVANT STRATEGIC GOALS:

Operational Excellence, Quality of Place

PROOF OF PUBLICATION:

N/A

body

BACKGROUND:

On April 18, 2023, Council approved the award of the Agreement for Drainage Rehabilitation Improvement Projects (DRIP) to Marion Rock, LLC, (Contract No.: CIP/230150) for an initial two-year term with two optional one-year renewals.  Council approved the first renewal term on April 15, 2025. 

During the last three years, Marion Rock, LLC, supported the Stormwater Division with the construction and maintenance of stormwater systems, totaling $4,200,000 in expenditure.

FINDINGS AND CONCLUSIONS:

For the final one-year renewal term, Marion Rock LLC’s unit prices will increase by 3 percent (as requested by the vendor and allowed by the agreement). Marion Rock has done an outstanding job supporting the City’s Stormwater Division facilities.  This final term will begin on May 9, 2026, and terminate on May 8, 2027.  City staff recommends approval of the final one-year renewal of the contract with Marion Rock, LLC for an amount not to exceed $1,250,000.

 

FISCAL IMPACT:

Funding is available in Fiscal Year 2025-26 in account 158-020-343-538-69-65010. Additional funding will be budgeted in Fiscal Year 2027 in the amount of $900,000.

 

PROCUREMENT REVIEW:

These goods and services were procured in compliance with the City’s Procurement Policy.

LEGAL REVIEW:

This Amendment will be reviewed and approved for form and legality by City Attorney, William E. Sexton.

ALTERNATIVE:

                     Approve with Changes

                     Table