Legislation Details

File #: 2026-1646   
Type: Agenda Item Status: Passed
File created: 6/12/2026 In control: City Council
On agenda: 7/7/2026 Final action: 7/7/2026
Title: Mockingbird Ridge Conceptual Subdivision
Attachments: 1. City Engineer Approval.pdf, 2. Aerial Map.pdf, 3. Case Map.pdf, 4. Conceptual Subdivision Plan.pdf, 5. Boundary Survey.pdf, 6. PD Plan.pdf, 7. PD Standards.pdf
Submitted By: Karen Cupp
presenter
Presentation By: Aubrey Hale
end
Department: Growth Management

FORMAL TITLE:
title
Mockingbird Ridge Conceptual Subdivision
end

OCALA'S RELEVANT STRATEGIC GOALS:
Quality of Place

PROOF OF PUBLICATION:
N/A

body
BACKGROUND:
This conceptual subdivision is for Mockingbird Ridge Phases 1-3 of the four-phase Mockingbird Ridge Planned Development. Proposed Phases 1-3 comprise a single-family residential subdivision with 493 lots, five tracts, and 3.74 miles of roadway on 169.38 acres.

The developer is Boyd Development LLC.

The plan was prepared by Kimley-Horn & Associates.

The property is zoned Planned Development (PD) and is part of the Heathbrook Development of Regional Impact.

Key Points:
* The concept plan identifies three phases for the development of this subdivision.

* Lot Setbacks: Front - 20 feet
Side - five feet (20 feet for street side-yard setback)
Rear - 10 feet

* Lots will be a minimum of 50 feet wide, with a minimum lot area of 6,000 square feet.

* The typical residential right-of-way is 50 feet with curb and gutter, 10-foot utility easements, and five-foot sidewalks on both sides.

* Roadways, drainage retention areas, and the conveyance system are proposed for private maintenance by the Homeowners' Association (HOA) and Community Development District (CDD).

* Potable water and sanitary sewer systems will be publicly maintained following the standard one-year maintenance period.

FINDINGS AND CONCLUSIONS:
* The conceptual subdivision plan is designed in accordance with the approved PD plan and Standards Book.

* A developer's agreement for the subdivision is required with the improvement plan submittal and must be approved and recorded prior to submitting the final plat application.

* The amenity center, shown as Tract C, requires a site plan for development.

* The conceptual subdivision plan (Case No. SUB25-0016) was recommended for approval by the Planning and Zoning Commissi...

Click here for full text