Title: Approve award of contract with All Webbs Enterprises, Inc., for the construction of two Upper Floridan Aquifer Wells at Water Treatment Plant No. 2 with a bid of $1,117,700 plus a 10 percent contingency of $111,770 and the cost of nine alternate bid items equaling $250,000 for a total expenditure of $1,479,470
Attachments: 1. FOR COUNCIL -Agreement for Drilling Two UFA Wells -WTP#2 - All Webbs Enterprises, Inc (ENG 250268), 2. Bid Tabulation (ENG 250268), 3. 9-28-21 Council Approval
Submitted By: Jimmy Lopez
presenter
Presentation By: Sean Lanier
end
Department: Engineering

STAFF RECOMMENDATION (Motion Ready):
title
Approve award of contract with All Webbs Enterprises, Inc., for the construction of two Upper Floridan Aquifer Wells at Water Treatment Plant No. 2 with a bid of $1,117,700 plus a 10 percent contingency of $111,770 and the cost of nine alternate bid items equaling $250,000 for a total expenditure of $1,479,470
end

OCALA'S RELEVANT STRATEGIC GOALS:
Operational Excellence, Quality of Place

PROOF OF PUBLICATION:
Bid released to the public: 1/22/2025: Newspaper ad published 1/24/2025

body
BACKGROUND:
This Project consists of drilling two (2) 24-inch diameter Upper Floridan Aquifer Wells. These wells (No. 11 and No. 12) will be located at the future Water Treatment Plant No. 2 (WTP#2) site for redundancy in our water availability throughout the City of Ocala (City). WTP# 2 is located at 3744 South Pine Avenue.

This Project is partially funded by cost-share agreement No. 37150, approved by Council on September 28, 2021, between the City and St. Johns River Water Management District for the Lower Floridan Aquifer Conversion Phase 3 Project.

FINDINGS AND CONCLUSIONS:
On January 22, 2025, the City of Ocala issued Invitation to Bid (ITB) No. ENG/250268 for Well Drilling at Water Treatment Plant No.2 - Upper Floridan Aquifer Well No. 11 and No. 12. On February 27, 2025, two bids were received on a unit price basis as follows:



All Webbs Enterprises, Inc. (All Webbs), was found to be the lowest responsible and responsive bidder, with a total bid of $1,117,700. Staff requests a 10 percent contingency of $111,770 to allow the City Engineer to issue change orders to cover unforeseen conditions and other conflicts that may arise during construction, as well as an additional $250,000 to cover the cost of nine alternate bid items (these alternate bid items include well abandonment/grout filling and modifications to 9 wells). ...

Click here for full text