Submitted By: Matthew Grow
presenter
Presentation By: Matthew Grow
end
Department: Aviation
STAFF RECOMMENDATION (Motion Ready):
title
Adopt Budget Resolution 2025-149 amending the Fiscal Year 2024-25 budget to appropriate $116,081 in grant funding from the Florida Department of Transportation and transfer $29,020 from the Airport reserve for projects account to design parcel infrastructure at the Ocala International Airport for a total amount of $145,101
end
OCALA'S RELEVANT STRATEGIC GOALS:
Economic Hub, Quality of Place
PROOF OF PUBLICATION:
NA
body
The A12 corporate hangar development site is an undeveloped, 5-acre parcel with direct airfield access. The City has issued several public advertisements seeking developers interested in developing all or part of the site. However, these efforts did not yield viable responses, primarily due to the significant site preparation required. This includes extensive grading, installation of all horizontal utilities, taxilane pavement, and the extension of a frontage road.
This grant will fund the design of these horizontal improvements, to begin construction later this year or in early 2026. The design will create three to four parcels, each capable of accommodating a 20,000 sq. ft. hangar and four additional parcels for 6,400 sq. ft. hangars. The total infrastructure cost will be averaged across the developable parcels, and prospective builders will be responsible for their proportional share of those costs as part of the vetting process for a long-term ground lease agreement.
FINDINGS AND CONCLUSIONS:
* Infrastructure, Consulting and Engineering, PLLC (ICE) is the consultant responsible for the design work, operating under an existing general consulting agreement (AIR/220118), dated July 20, 2022.
* The Airport Advisory Board has expressed its support for the project.
* Staff is coordinating the project with the City Engineer.
* The project is consistent with the Airport Master Plan.
* Staff will coordina...