Title: Approve one-year renewal agreement with Service and Technology Network Solutions, Inc. for the provision of conduit installation services in the amount of $750,000
Attachments: 1. FOR COUNCIL - Second Amendment - Conduit Installation Services - Service and Technology Network Solutions (OFN-200747, 2. Fully Executed - First Amendment - Conduit Installation Services - Service and Technology Network Solutions (OFN-200747).pdf, 3. Fully Executed - Original Agreement - Service and Technology Network Solutions - Conduit Installation Services (OFN 200747).pdf, 4. Council Report - 11-17-2020 - Conduit Installation - OFN 200747.pdf, 5. 2022 S&T Renewal Letter Signed 08.26.22, 6. Consent to Renewal Terms S&T Network Solutions Contract #200747 Renewal, 7. Consent to Renewal Terms for OFN Contracts 200747 & 200700
Submitted By: Lourdes Ramos
presenter
Presentation By: Mel Poole
end
Department: Ocala Fiber Network

STAFF RECOMMENDATION (Motion Ready):
title
Approve one-year renewal agreement with Service and Technology Network Solutions, Inc. for the provision of conduit installation services in the amount of $750,000
end

OCALA'S RELEVANT STRATEGIC GOALS:
Operational Excellence

PROOF OF PUBLICATION:
N/A

body
BACKGROUND:
On November 17, 2020, City Council approved a two-year contract with Service and Technology Network Solutions, Inc. ("S&T"), Contract No. OFN/200747 ("the Original Agreement"), for the provision of conduit installation services on an as needed basis with an aggregate expenditure amount of $2,800,000. The initial term of the Original Agreement was effective through November 16, 2022, and provided two (2) optional one-year renewal terms. On November 17, 2022, City Council approved the first one-year renewal with S&T in the amount of $750,000.
OFN is now seeking approval of the second one-year renewal with S&T for $750,000. The provision of these services is critical to OFN's ongoing installation of fiber cables, service drops, and potential storm-damage restoration.

FINDINGS AND CONCLUSIONS:
OFN recommends approval of the contract renewal with S&T to support customer growth and network reliability.

FISCAL IMPACT:
The funding for the contract is available in the following account strings:

FY 24 490-031-291-539-64-63020 Improvement O/T Buildings-Adding to Customer Base $324,000

FY 25 490-031-291-539-64-63020 Improvement O/T Buildings-Adding to Customer Base $30,000

FY 24 490-031-292-539-64-63020 Improvement O/T Buildings-Road Projects $336,000

FY 25 490-031-292-539-64-63020 Improvement O/T Buildings-Road Projects $60,000

PROCUREMENT REVIEW:
These services were procured in compliance with the City's Procurement Policy.
LEGAL REVIEW:
This renewal amendment will be reviewed and approved for form and legality by City Attorney, Willi...