Adopt Budget Resolution 2024-120 appropriating funds from the Florida Department of Environmental Protection for the Ocala Force Main Construction Project in the amount of $500,000
end

OCALA’S RELEVANT STRATEGIC GOALS:
Operational Excellence, Quality of Place

PROOF OF PUBLICATION:
N/A

body
BACKGROUND:
The southwest area of Ocala (Winding Oaks) will have approximately 4,000 new homes that will require access to a centralized sanitary sewer system in the near future. Based on the Wastewater Master Plan of 2019, there is a list of projects to be completed to provide sanitary service to this area. The Lift Station #127 Force Main Upgrade is the next project to be completed on this list. The project consists of installation of approximately 6,000 linear feet of 18-inch force main on SW 48th Avenue. This project was already designed by the Water Resources Engineering division.
FINDINGS AND CONCLUSIONS:
The Florida Department of Environmental Protection (FDEP) is granting $500,000 for the installation of approximately 6,000 linear feet of 18-inch force main that will upgrade the lift station #127 force main and will eventually extend the sewer service to the Winding Oaks area. This grant will cover a portion of the total project cost.
FISCAL IMPACT:
FDEP agrees to reimburse the City in an amount not to exceed $500,000 which will be appropriated in account #308-050-367-535-69-65010.
PROCUREMENT REVIEW:
N/A
LEGAL REVIEW:
N/A
ALTERNATIVE:
• Adopt with Changes
• Table
• Deny
BUDGET RESOLUTION 2024-120
A RESOLUTION AMENDING THE FISCAL YEAR 2023-24 BUDGET TO ACCEPT AND APPROPIATE FUNDS FROM THE FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION FOR THE OCALA FORCE MAIN CONSTRUCTION PROJECT IN THE AMOUNT OF $500,000
WHEREAS, the City has been awarded a grant from the Florida Department of Environment Protection (LPA0596) in the amount of $500,000 for the Ocala Force Main Construction Project; and
WHEREAS, the grant is for the installation of approximately 6,000 linear feet of 18-inch force main that will upgrade the lift station #127 force main and will eventually extend the sewer service to the Windings Oaks area; and
WHEREAS, this grant does not require any matching funds from the City.
NOW THEREFORE, BE IT RESOLVED THAT THE CITY COUNCIL OF THE CITY OF OCALA, FLORIDA, duly assembled in regular session, that the Fiscal Year 2023-24 budget be amended as outlined below.
SOURCE:
308-334-000-000-09-33473 Fl Dept Environ Protection $500,000
USE:
308-050-367-535-69-65010 Construction in Progress $500,000
This resolution adopted this ______ day of ______________________, 2023.
ATTEST: CITY OF OCALA
By: By:
Angel B. Jacobs James P. Hilty Sr.
City Clerk President, Ocala City Council
Approved as to form and legality:
By: _________________________________
William E. Sexton
City Attorney
Reviewed for accounting accuracy & completeness:
By: _________________________________
Peter A. Lee
City Manager