File #: 2025-2104   
Type: Agenda Item Status: Agenda Ready
File created: 9/17/2025 In control: City Council
On agenda: 10/7/2025 Final action:
Title: Task Work Order No. 5 with Tillman & Associates Engineering, LLC, for the provision of Professional Engineering Services for the design of a permanent pump station for Fisher Park Drainage Retention Area in the amount of $69,920 and increase the aggregate expenditure threshold by $75,000
Attachments: 1. FOR COUNCIL - VERIFIED - TWO #5 - Fisher Park DRA - Tillman & Assocates (ENG 220333), 2. FULLY EXECUTED CONTRACT-First_Amendment_to_Agreement_for_Continuing_P (6), 3. FULLY EXECUTED - Continuing Professional Services Agreement - Citywide - Tillman & Associates Engineering, LLC (ENG 220333)
Date Action ByMotionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted By: Payal Pandya

presenter

Presentation By: Sean Lanier

end

Department: Engineering

FORMAL TITLE:

title

Task Work Order No. 5 with Tillman & Associates Engineering, LLC, for the provision of Professional Engineering Services for the design of a permanent pump station for Fisher Park Drainage Retention Area in the amount of $69,920 and increase the aggregate expenditure threshold by $75,000

end

OCALA’S RELEVANT STRATEGIC GOALS:

Quality of Place.

PROOF OF PUBLICATION:

N/A

body

BACKGROUND:

The project consists of engineering design of a permanent pump station adjacent to the Drainage Retention Area (DRA) at Fisher Park to aid in the recovery of capacity in the DRA after storm events and mitigate historical flooding.

The Engineering Department contacted Tillman & Associates Engineering, LLC for a proposal for the design of a permanent pump station adjacent to the Drainage Retention Area (DRA) at Fisher Park.  Design services are being provided in accordance with the Agreement for Continuing Professional Engineering Services, (Contract No. ENG/220333) approved by the City Council on September 20, 2022 and amended on August 19, 2025.

 

FINDINGS AND CONCLUSIONS:

The scope of this Task Work Order includes planning, design, and permitting of pump station which shall be prepared and submitted as a single, comprehensive set of construction plans and specifications, to be permitted and constructed as one phase.

On August 19, 2025, the City Council approved the first amendment to the Continuing Professional Engineering Services Agreement (Contract No. ENG/220333) with Tillman & Associates Engineering, LLC, with an aggregate expenditure threshold of $150,000.  The first amendment contract term begins on October 1, 2025, and expires on September 30, 2026.

Staff requests approval of Task Work Order No. 5, to allow Tillman & Associates, LLC to provide engineering services for the project, and an increase to the aggregate expenditure threshold on Contract No. ENG/220333 by $75,000 to cover the cost of this Task Work Order.

 

FISCAL IMPACT:

Funding for this Task Work Order is available in account string 158-020-430-538-53-31010 in the amount of $69,920.

 

PROCUREMENT REVIEW:

These services were procured, and Task Work Order reviewed, in compliance with the City’s procurement policy.

 

LEGAL REVIEW:

The amended agreement has been reviewed and approved for form and legality by City Attorney, William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table