File #: 2025-0084   
Type: Agenda Item Status: Passed
File created: 10/21/2024 In control: City Council
On agenda: 12/3/2024 Final action: 12/3/2024
Title: Approve agreement with SSC Construction Management, LLC for design-build services for the Downtown Parking Garage No. 2 in the amount of $17,481,485.70 plus a contingency amount of $974,497.30, for a total expenditure of $18,455,983
Attachments: 1. NOTICE OF INTENT TO AWARD, 2. FOR_COUNCIL_-_Professional_Services_Agreement_for_Design_Build_Servicees_-_Downtown_Garage_No_2_(ENG, 3. ParkingGarage#2 - EXHIBIT A - Scope of Services, 4. ParkingGarage#2 - EXHIBIT B - Design Criteria Package, 5. ParkingGarage#2 - EXHIBIT C - Design-Builder Proposal, 6. ParkingGarage#2 - EXHIBIT D - Project Schedule (rev 11-17-24), 7. ParkingGarage#2 - EXHIBIT E - Price Proposal

Submitted By: Paul Constable

presenter

Presentation By: Sean Lanier

end

Department: Engineering

STAFF RECOMMENDATION (Motion Ready):

title

Approve agreement with SSC Construction Management, LLC for design-build services for the Downtown Parking Garage No. 2 in the amount of $17,481,485.70 plus a contingency amount of $974,497.30, for a total expenditure of $18,455,983

end

OCALA’S RELEVANT STRATEGIC GOALS:

Quality of Place, Operational Excellence

PROOF OF PUBLICATION:

Bid released to the public: 04/15/2024; Newspaper ad published 04/19/2024

body

BACKGROUND:

On April 15, 2024, the City issued a request for proposals from professional design-build teams to provide conceptual designs, final design, construction documents, and construction services for the construction of a multi-story parking garage with a minimum of 800 parking spaces to be located at the City block encompassed by West Broadway Street to the north, SW Third Avenue to the west, SW Second Avenue to the east and West Fort King Street to the south.

 

FINDINGS AND CONCLUSIONS:

On June 14, 2024, the City received two qualified and responsive proposals. A selection committee met to review the two proposals for qualifications, availability, experience, and price. Both firms were shortlisted and requested to provide presentations.

 

The shortlisted firms that provided presentations were:

                     SSC Construction, LLC                                                                                    Ocala, FL

                     Finfrock Construction, Inc.                                                                                    Apopka, FL

 

 

The firms were scored by ordinal ranking. The selection committee members ranked SSC Construction, LLC first and Finfrock Construction, Inc. second.

 

SSC Construction presented the committee with the desired aesthetics, construction, and price the City sought. Therefore, they recommend an award to SSC Construction, LLC.

 

This project is partially funded by the American Rescue Plan Act (ARPA). On June 6, 2023, the City Council approved Budget Resolution #2023-144 to accept the ARPA funds and designate $3,242,323 for the project. 

 

Parking Garage No. 2 is projected to be completed by June 2026.

 

FISCAL IMPACT:

Funding for this project is budgeted in the following accounts:

120-020-328-545-69-65010:  $14,495,460

332-032-328-531-69-65010:  $700,000

490-031-328-539-69-65010:  $18,200

001-060-332-545-69-65010:                     $3,242,323

 

PROCUREMENT REVIEW:

These services were procured in compliance with the City’s procurement policy. 

 

LEGAL REVIEW:

This Agreement will be reviewed and approved for form and legality by City Attorney, William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny