File #: 2025-1072   
Type: Agenda Item Status: Passed
File created: 4/2/2025 In control: City Council
On agenda: 4/15/2025 Final action: 4/15/2025
Title: Approve award of contract to C.W. Roberts Contracting, Inc. for the State Road 40 traffic signalization project at SW/NW 46th Avenue in the amount of $1,897,490, plus 10 percent contingency, for a total expenditure not to exceed $2,087,239
Attachments: 1. FOR COUNCIL -Agreement for Signalization of SW_NW 46th Avenue at SR 40 - CW Roberts Contracting, Inc (CIP 250303)-1, 2. BID TABULATION, 3. Plan Set, 4. NWSW 44th Ave Extension R1

Submitted By: Paul Constable

presenter

Presentation By: Sean Lanier

end

Department: Engineering

STAFF RECOMMENDATION (Motion Ready):

title

Approve award of contract to C.W. Roberts Contracting, Inc. for the State Road 40 traffic signalization project at SW/NW 46th Avenue in the amount of $1,897,490, plus 10 percent contingency, for a total expenditure not to exceed $2,087,239

end

OCALA’S RELEVANT STRATEGIC GOALS:

Operational Excellence, Quality of Place

PROOF OF PUBLICATION:

Bid released to the public: 1/30/2025; Newspaper ad published 1/31/25

body

BACKGROUND:

The State Road 40 signalization project at SW/NW 46th Avenue consists of constructing a new traffic signal, a directional bore for water main connection, and sidewalk construction. Signalization improvements will include constructing concrete strain poles, traffic signals, ITS and smart signal technology, pedestrian signals and detectors, pavement markings, signage, and street lighting.

 

Once completed, this project will connect the southwest and northwest portions of the 44th Avenue Extension projects through State Road 40.

 

FINDINGS AND CONCLUSIONS:

On January 30, 2025, the City of Ocala (City) issued Invitation to Bid (ITB) No.: CIP/250303 for construction services for the State Road 40 signalization project at SW/NW 46th Avenue. On March 19, 2025, one bid was received from CW Roberts Contracting, Inc. (CWR) on a unit price basis.

 

 

CWR was the lone responsive bidder to the ITB. The bid duration was extended for two weeks to allow for additional responsive bidders; however, none were received. CWR submitted a total bid of $1,897,490 utilizing an alternate bid item. 

 

Staff requests a 10 percent contingency of $189,749 to allow the City Engineer to issue change orders to cover unforeseen conditions and other conflicts that may arise during construction. With the contingency, the total project budget is not to exceed $2,087,239.

 

CWR has previously completed construction projects for the City, and their performance has been very satisfactory. Staff recommends awarding the contract to CWR for the construction of the signalization project at State Road 40 and SW/NW 46th Avenue.

 

FISCAL IMPACT:

Funding for this project is budgeted in the following accounts:

120-020-386-541-69-65010 - $1,500,000

091-020-386-541-69-65010 - $587,239

 

PROCUREMENT REVIEW:

These services were procured in compliance with the City’s Procurement Policy.

 

LEGAL REVIEW:

This Agreement will be reviewed and approved for form and legality by City Attorney, William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny