Submitted By: Paul Constable
presenter
Presentation By: Sean Lanier
end
Department: Engineering

FORMAL TITLE:
title
Contract with Joseph Hoffman Construction, LLC to provide all labor, materials, equipment, and services necessary for the construction of concrete pads and T-hanger taxilane rehabilitation at Ocala International Airport for a total expenditure not to exceed $932,932
end

OCALA’S RELEVANT STRATEGIC GOALS:
Operational Excellence

PROOF OF PUBLICATION:
Bid released to the public: 9/9/2026; Newspaper ad published: 9/18/2026

body
BACKGROUND:
The Ocala International Airport (OCF) has identified key locations for infrastructure improvements designed to enhance the operational capacity and efficiency of the airport’s general aviation and maintenance activities. These locations include three areas requiring concrete pavement rehabilitation and a separate location requiring T-hangar taxilane rehabilitation. The proposed improvements will improve airfield access, increase operational efficiency, and support the continued growth of airport operations.
On May 6, 2025, the City adopted Budget Resolution No. 2025-152, authorizing the acceptance and appropriation of $543,320 through a Public Transportation Grant Agreement (PTGA) with the Florida Department of Transportation (FDOT) for the design and construction of fuel farm, wash rack, and parking area concrete pads, as well as the rehabilitation of the T-Hangar taxilane at OCF. The resolution also authorized the transfer of $135,830 from OCF reserves account to provide the required local matching funds (20%).
On March 3, 2026, the City adopted Budget Resolution No. 2026-131, authorizing the acceptance and appropriation of an additional $478,285 through a supplemental PTGA with FDOT to continue these improvements. The resolution further authorized the transfer of $119,572 from OCF reserves account to satisfy the corresponding local match requirement (20%).
Collectively, Budget Resolutions No. 2025-152 and No. 2026-131 authorized the acceptance and appropriation of $1,021,605 in FDOT grant funding. In addition, the resolutions authorized a total local match contribution of $255,402 from OCF reserves account, resulting in total project funding of $1,277,007.
FINDINGS AND CONCLUSIONS:
On September 9, 2026, the City issued its Invitation to Bid (“ITB”) No.: AIR/261130 for Construction of Concrete Pads and T-Hanger Taxilane Rehabilitation at OCF. On October 23, 2026, four bids were received, on a unit price basis as follows:

Joseph Hoffman Construction, LLC was found to be the lowest responsive and responsible bidder with a total bid of $848,120.
Staff requests a 10 percent contingency of $84,812 to allow the City Engineer to issue change orders for unforeseen conditions and other conflicts that may arise during construction. With the contingency, the total project budget is not to exceed $932,932.
Staff has reviewed the qualifications and experience of Joseph Hoffman Construction, LLC and confirmed the firm's successful completion of a similar airport project with favorable owner references. Based on the firm's demonstrated capabilities and project history, staff recommends awarding the contract to Joseph Hoffman Construction, LLC to construct concrete pads and rehabilitate the T-hangar taxilane at Ocala International Airport.
FISCAL IMPACT:
The project total is $932,932 and is appropriated in the following manner:
• $746,345.60 in FDOT grant account #341-050-722-542-54-31010
• $186,586.40 in local Airport match account #451-027-722-542-54-31010.
PROCUREMENT REVIEW:
These services were procured in compliance with the City’s procurement policy.
LEGAL REVIEW:
This Agreement will be reviewed and approved for form and legality by City Attorney, William E. Sexton.
ALTERNATIVE:
• Approve with Changes
• Table
• Deny