Skip to main content
City of Ocala Logo

  For historical data from all meetings prior to January 18, 2022, please refer to our archived meeting repository.

File #: 2024-1906   
Type: Agenda Item Status: Passed
File created: 7/31/2024 In control: City Council
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Approve the award of the contract for the construction of the North Complex Trailer Yard Shed to Genesis Construction & Management, Inc., in the amount of $313,194, plus a 10 percent contingency of $31,319.40, for a total expenditure not to exceed $344,513
Attachments: 1. FOR COUNCIL - Construction Services Agreement for North Complex Trailer Yard Shed - Genesis Construction & Management, Inc (CIP 240746), 2. Proof of Publication 240746 run 6-21-2024, 3. BID TABULATION

Submitted By: Jimmy Lopez

presenter

Presentation By: Sean Lanier

end

Department: Engineering

STAFF RECOMMENDATION (Motion Ready):

title

Approve the award of the contract for the construction of the North Complex Trailer Yard Shed to Genesis Construction & Management, Inc., in the amount of $313,194, plus a 10 percent contingency of $31,319.40, for a total expenditure not to exceed $344,513

end

OCALA’S RELEVANT STRATEGIC GOALS:

Operational Excellence

PROOF OF PUBLICATION:

Bid released to public: 6/18/2024; Newspaper Ad: 6/212024

body

BACKGROUND:

This project consists of the construction of a 160-foot x 35-foot x 19-foot 5-inch open bay, covered steel structure. This structure will have six bays, designed with an interior roof clearance of 13 feet and seven inches, and a concrete floor.  The structure will be used to park and store equipment, trailers, and tools utilized by the Ocala Fiber Network Department.

 

FINDINGS AND CONCLUSIONS:

On June 18, 2024, the City of Ocala issued Invitation to Bid (ITB) No. CIP/ 240746 for the North Complex Trailer Yard Shed. On July 24, 2024, five bids were received on a Lump Sum basis as follows:

 

 

Genesis Construction & Management, Inc. was found to be the lowest responsible bidder, with a total bid of $313,194. Staff requests a 10 percent contingency for $31,319.40 to allow the City Engineer to issue change orders to cover unforeseen conditions and other conflicts that may arise during construction. With the contingency, the total project budget will not exceed $344,513.40.

 

Genesis Construction & Management, Inc. has satisfactorily completed similar projects for the City in the last five years. Staff recommends awarding the contract to Genesis Construction & Management, Inc. for the construction of the North Complex Trailer Yard Shed.

 

FISCAL IMPACT:

Funding for this contract is budgeted as follows:   490-031-288-539-69-65010                     $344,513.40

 

PROCUREMENT REVIEW:

These services were procured per the City’s Procurement Policy. 

 

LEGAL REVIEW:

This Agreement will be reviewed and approved for form and legality by City Attorney William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny