File #: 2023-0321   
Type: Agenda Item Status: Passed
File created: 12/15/2022 In control: City Council
On agenda: 1/3/2023 Final action: 1/3/2023
Title: Approve Change Order #1 with Gee Asphalt Systems, Inc. for asphalt crack seal/fog seal of Runway 18/36 at Ocala International Airport in the amount of $76,064
Attachments: 1. Change Order #01, 2. Construction Services Agreement for Asphalt Crack Seal Runway 18-36 (AIR 210428), 3. FDOT Grant Amendment 1 (449123-1-94-01), 4. FDOT Grant Agreement (449123-1-94-01), 5. FDOT Grant Amendment 2 (449123-1-94-01), 6. FAA Grant 3-12-0055-030-2021

Submitted By: Matthew Grow

presenter

Presentation By: Matthew Grow

end

Department: Aviation

STAFF RECOMMENDATION (Motion Ready):

title

Approve Change Order #1 with Gee Asphalt Systems, Inc. for asphalt crack seal/fog seal of Runway 18/36 at Ocala International Airport in the amount of $76,064

end

OCALA’S RELEVANT STRATEGIC GOALS:

Operational Excellence

PROOF OF PUBLICATION:

NA

body

BACKGROUND:

On November 2, 2021, City Council approved the contract for asphalt crack seal/fog seal of Runway 18/36 with Gee Asphalt Systems, Inc. (“Gee”) for $256,596.  This work was contingent on the completion of other work. However, due to scheduling and contract issues along with weather limitations, completion of that work was not finalized until April 2022.  This pushed the contract with Gee six (6) months further resulting in unit price increases. 

FINDINGS AND CONCLUSIONS:

On May 18, 2021, City Council approved the acceptance of a Public Transportation Grant Agreement (“PGAT”) No. 449123-1-94-01 from the State of Florida Department of Transportation (“FDOT”) to fund the re-painting of airfield markings on Runway 18/36 at the Ocala International Airport for a project cost of $189,000 and grant amount of $151,200.

On July 20, 2021, City Council approved the acceptance of an Airport Improvement Program (“AIP”) Grant Agreement No. 3-12-0055-030-2021 from the Federal Aviation Administration (“FAA”) for fog-sealing pavement and joints at the Ocala Airport. This $298,971 FAA grant included the construction and inspection costs associated with the sealing of Runway 18/36 pavement and joints.

 

On October 5, 2021, City Council approved the first amendment to the FDOT grant that facilitated additional paint for a project cost at that time of $211,150 and grant amount of $168,920.

 

On April 19, 2022, City Council approved the second amendment to the FDOT grant to facilitate Change Order #1 with Gee Asphalt Systems, Inc. for a total project cost of $291,550 and total grant amount of $233,240.

This Change Order #1 for $76,064 results in a revised contract amount of $332,660.  The amended grant from the Florida Department of Transportation covered $64,320 of the change order with the Airport funding the remaining $11,744. 

All work was completed in November 2022.

 

FISCAL IMPACT:

This Change Order is funded by:

FDOT:                       $64,320                     341-050-767-542-69-65010

LOCAL:                      $11,744                     451-027-767-542-69-65010

TOTAL:                     $76,064

 

PROCUREMENT REVIEW:

The services were procured in compliance with the City’s Procurement Policy. 

 

LEGAL REVIEW:

The underlying Agreement was reviewed and approved for form and legality by the prior City Attorney, Robert W. Batsel, Jr.

 

ALTERNATIVE:

                     Approve with Changes

                     Table

                     Deny