File #: 2024-2236   
Type: Agenda Item Status: Passed
File created: 9/10/2024 In control: City Council
On agenda: 11/5/2024 Final action: 11/5/2024
Title: Approve award of contract to Bruce Wayne Wiley LLC for residential rehabilitation services for the Follins residence located at 2411 NW Second Street with a total project cost not to exceed $61,380
Attachments: 1. FOR COUNCIL - Agreement for Rehabilitation of Home -Follins- Bruce Wayne Wiley (CDS 240731), 2. BID TABULATION Follins Bid

Submitted By: James Haynes

presenter

Presentation By: James Haynes

end

Department: Community Development Services

STAFF RECOMMENDATION (Motion Ready):

title

Approve award of contract to Bruce Wayne Wiley LLC for residential rehabilitation services for the Follins residence located at 2411 NW Second Street with a total project cost not to exceed $61,380

 

end

OCALA’S RELEVANT STRATEGIC GOALS:

Quality of Place

PROOF OF PUBLICATION:

Bid Released to Public: 5/30/2024

body

BACKGROUND:

On or about September 28, 2023, the City’s Community Development Services (CDS) Department received a request for assistance with housing rehabilitation from a low-income family. CDS conducted a structural evaluation of the home. To bring the house to current building standards, the home requires plumbing and electrical upgrades, interior repairs and painting; two bathroom remodels to include ADA accessibility, and flooring replacement throughout the house.

 

 

FINDINGS AND CONCLUSIONS:

On May 30, 2024, the City issued Request for Quotes (“RFQ”) No. CDS/240731 via its e-procurement system, ProRFX, for the provision of Residential Rehabilitation of the Follins residence.  A total of 1,100 vendors registered in the ProRFX system under the following commodity codes were notified of the opportunity:  

                     [72111006] Single-family home new construction service

                     [72111111] General residential construction contractor service

On July 3, 2024, bids were received from six contractors. The bid from Building Vision Construction, LLC was rejected as non-responsive. Bid results for the remaining responsive bidders are summarized below.

 

Bruce Wayne Wiley, LLC was found to be the lowest responsible bidder, with a total bid of $61,380. This action is consistent with the City's Low Housing Assistance Plan (LHAP). Under the State Housing Initiatives Partnership (SHIP) program, the homeowner is required to sign a deferred 20-year mortgage.

 

FISCAL IMPACT:

Funding in the amount of $61,380 will come from SHIP account number 140-050-699-559-55-34010.

 

PROCUREMENT REVIEW:

These services were procured in compliance with the City’s procurement policy. 

 

LEGAL REVIEW:

This Agreement will be reviewed and approved for form and legality by City Attorney, William E. Sexton.

 

ALTERNATIVE:

                     Approve with Changes

                     Table